New Life Baptist Church - Multipurpose Facility
Owner: New Life Baptist Church
Delivery Method: Construction Management at Risk
size
165,000 square feet
Cost
$3,765,210
duration
5 months
Design Partners:
Rees Architecture
Superintendent:
Wayne Bradley
The Blue River Group was brought on board to complete phase I of the New Life Baptist Church project after the previous contractor had been released from the project. Initial services included forensic investigation to determine repairs necessary to the site, building envelop and incomplete MEP systems to determine what was necessary to obtain a Certificate of Occupancy for the entire building and site to allow for the church to move into a portion of the interior spaces to be used for these functions. Phase I of the project was completed to the entire team’s satisfaction.